Write down once what goes into each product, so production, costing and purchasing all work from the same recipe.

Open this area in your workspace

What a bill of materials holds

A bill of materials (BOM) is the recipe for an item you make: the components it uses, how much of each, and how many finished units one run produces. A desk bill might make 1 desk from 1.5 sheets of 18 mm MDF, 6 m of edge banding, 4 steel legs and 24 screws. Bills of materials come with the Make and Custom plans.

Each component line can use its own unit. Buy edge banding in rolls of 50 m and use it in metres: the line records the unit and its factor to the base unit, so stock always moves in base units.

Create a bill of materials

An item can have more than one bill, for example a standard recipe and one with a substitute material. Keep one as the default, and switch a bill off when you stop using it. Production orders already made keep the bill they used.

  1. Open Bills of materials and choose the item the bill makes.
  2. Name the bill and enter the quantity one run produces, in the item’s base unit.
  3. Add a line for each component with its quantity per run and the unit you measure it in.
  4. Where some material is always lost, such as saw cuts or cream left in the mixer, enter a planned waste percentage on that line. Production then consumes the quantity plus the waste.
  5. Mark the bill as the item’s default. New production orders start from the default bill.

Sub-assemblies: bills inside bills

A component can be something you make yourself. A meeting table might use a steel frame that your workshop welds from tubes and plates. Give the frame its own bill of materials, make it with its own production order, then use it as a component in the table’s bill. Each level is costed from what it actually consumed.

Because the frame is an item with its own stock, you also see how many finished frames are on the shelf, ready for the next order.

By-products and offcuts

Some runs leave something worth keeping: offcuts large enough for shelves, or trimmings you sell by weight. Add them to the bill as outputs, with a quantity per run. When production is recorded, they arrive in stock next to the main product instead of disappearing as waste.

Each by-product can carry a share of the run’s cost, as a percentage. Give offcuts a small share and the main product carries the rest, so both are valued sensibly.

What you see depends on your plan, the features your workspace has switched on and your access. If a screen in this guide is missing, ask your workspace owner.